Our proposals for the 2021-2026 regulatory period were submitted in January 2020. These proposals included decisions about the economic building blocks as they related to Powercor and CitiPower, including the way we treat incentives, tax, operating expenditure, depreciation and return on assets.
Regulatory Reset Timeline
Through the regulatory process we’ll deliver a blueprint to 2026 that considers input from customers and stakeholders about how they want to use, store and generate power now and into the future.
Here’s where we are in the process.
1
August 2017
Collect residential, small business, commercial and industrial customer insights
2
September 2017
Establishment of the Energy Futures Customer Advisory Panel
3
November 2017
Support the Victorian Electricity Networks Futures Forum on network pricing
4
November 2017
Host energy futures scenario and modelling forum
5
May 2018
Publish consultation paper on possible energy futures
6
June 2018
Hold customer and stakeholder forums to deliberate on possible future energy scenarios
7
September 2018
Publish report on customer and stakeholder feedback from forums
8
February 2019
Release our Draft Plans for consultation
9
June 2019
Publish reports on customer and stakeholder feedback about our Draft Proposals
10
April 2019
Host Future Networks Forum and IT and Risk Monsetisation round tables
11
January 2020
Proposal submitted to the Australian Energy Regulator
12
September 2020
Draft decision by the Australian Energy Regulator
13
December 2020
Revised Proposal submitted to the Australian Energy Regulator
14
April 2021
Final determination by the Australian Energy Regulator about our Proposal